Built Revenue Report
Track revenue recognition on production projects using the percentage of completion method.
Accessing the Report
Reports > Production > Built Revenue submenu:
- Built Revenue - Current built revenue
- Built Revenue Month over Month - Trend comparison
- Built Revenue Weekly - Weekly detail
Key Metrics
| Metric | Description |
|---|---|
| Contract Value | Total project contract |
| % Complete | Project completion percentage |
| Built Revenue | Revenue recognized to date |
| Billed to Date | Amount invoiced |
| Over/Under | Difference between built and billed |
Calculation Method
Built revenue uses percentage of completion:
Built Revenue = Contract Value × % Complete
Example
- Contract: $100,000
- % Complete: 60%
- Built Revenue: $60,000
Understanding Over/Under Billing
Over Billing
Billed > Built Revenue
- Customer paid ahead of work
- Positive for cash flow
- Liability until work catches up
Under Billing
Built Revenue > Billed
- Work ahead of billing
- Revenue earned, not yet invoiced
- Opportunity to bill
Report Views
Current Built Revenue
Point-in-time snapshot:
- All active production projects
- Current % complete
- Current billing status
Month over Month
Trend comparison:
- Built revenue by month
- Growth/decline patterns
- Seasonal analysis
Weekly Detail
Granular view:
- Week-by-week changes
- Progress tracking
- Recent activity focus
Available Filters
| Filter | Description |
|---|---|
| Date Range | As-of date or period |
| Division | Business unit |
| Project Manager | Filter by PM |
| Production Stage | Active stages |
Analysis Use Cases
Revenue Recognition
For accounting purposes:
- Month-end revenue calculation
- Financial statement support
- Audit documentation
Cash Flow Management
Identify billing opportunities:
- Large under-billing = invoice now
- Track billing efficiency
- Forecast cash inflows
Project Health
Spot potential issues:
- Progress stalled but billed ahead
- Progress moving but not billing
- Unusual patterns
Timing Considerations
Built revenue timing depends on:
- When % complete is updated
- Production stage changes
- Manual progress entries
Best Practice: Update % complete weekly minimum.
Export Options
Click Export CSV to download for:
- Accounting entries
- Management reporting
- Historical tracking
Tips
- Update % complete regularly for accuracy
- Review over-billing to ensure work catches up
- Bill under-billed projects promptly
- Compare to WIP Report for cross-validation
Related Reports
- WIP Report - Comprehensive financial view
- Project Completion - Final revenue analysis
- Active Production Jobs - % complete status