Cost Controls Report

Filtered Data

This report is filtered based on your division settings:

  • Function: Operational
  • Work Type: Full Project

Monitor budget performance with focus on labor hours and material costs across all production projects.

Accessing the Report​

Reports > Production > Cost Controls

Report Columns​

ColumnDescription
PIDProject ID (linked to project)
ClientClient name (Last, First format)
PMAssigned Project Manager
LeadLead Carpenter assigned
% Compl.Project completion percentage
Hours Used / ScopeActual hours vs. estimated hours
Hours Used %Percentage of labor budget consumed
Total Est. Material CostBudgeted material costs
Current PO CostTotal from purchase orders
Material Cost %PO costs as percentage of budget

Available Filters​

Access filters by clicking Show Filters button:

FilterDescription
Project ManagerFilter by assigned PM
Lead CarpenterFilter by lead
Project Start DateStart/end date range
DivisionProject category
Production StageCurrent production stage

Quick Year Filters​

Click year buttons to quickly set date range:

  • Previous year
  • Current year
  • Next year

Clear Filters​

Click Clear All Filters to reset all selections.

Reading the Report​

Hours Analysis​

The Hours Used / Scope column shows:

Actual Hours Worked / Total Estimated Hours

Example: 45.5 / 60.0 means 45.5 hours used of 60 estimated.

The Hours Used % shows this as a percentage:

Hours Used % = (Actual Hours ÷ Estimated Hours) × 100

Material Analysis​

The Material Cost % shows purchase order costs vs. budget:

Material Cost % = (PO Costs ÷ Estimated Material Cost) × 100

Visual Indicators​

Red text appears when:

  • Hours Used % exceeds 100%
  • Material Cost % exceeds 100%

This highlights projects running over budget.

Sorting​

Click any column header to sort:

  • Click once for ascending
  • Click again for descending
  • Sorted column is indicated visually

Key Metrics Explained​

% Complete​

Based on project progress tracking:

  • Updated by project manager
  • Reflects physical completion
  • May differ from cost-based completion

Hours Used %​

Labor budget consumption:

  • Under 100%: On or under labor budget
  • At 100%: Exactly on budget
  • Over 100%: Over labor budget

Material Cost %​

Material budget consumption:

  • Compares actual POs to estimated materials
  • Doesn't include materials not yet ordered
  • May show under 100% if POs pending

Export Options​

Click Export CSV to download:

  • All visible columns
  • Filtered results only
  • For spreadsheet analysis

Common Use Cases​

  1. Weekly production meeting: Review over-budget projects
  2. Project manager oversight: Check PM's portfolio status
  3. Lead carpenter review: Monitor crew performance
  4. Early warning system: Catch budget issues early

Analysis Tips​

Healthy Patterns​

  • Hours Used % roughly equals % Complete
  • Material Cost % tracks with project progress
  • Consistent patterns across similar projects

Warning Signs​

  • Hours Used % significantly ahead of % Complete
  • Material Cost % spiking unexpectedly
  • Projects at 50% complete but 80% of hours used

Actions for Over-Budget Projects​

  1. Review daily logs for issues
  2. Check for scope creep
  3. Verify time is logged correctly
  4. Discuss with PM and lead
  5. Consider change order if scope increased

Tips​

  • Review at least weekly during production
  • Sort by Hours Used % to find problem projects quickly
  • Compare similar project types for benchmarking
  • Use with Daily Log Report for detail investigation