Production Phase
The Production phase manages active construction, scheduling, and project progress tracking.
Overview
The Production tab provides:
- Production stage tracking
- Construction schedule and timeline
- Daily log access
- Punch list management
- Progress metrics
Production Stage Tracking
Projects move through production stages defined by your administrator. Common stages include:
- Pre-Construction
- Demolition
- Rough-In
- Finish Work
- Punch List
- Complete
Advancing Production Stages
- Click the current production stage
- Select the new stage
- Update percent complete if applicable
- Add any milestone notes
Production Dates
Production uses several date fields to track commitments, predictions, and actual progress. Understanding how these dates work together helps with accurate project planning and on-time delivery tracking.
Contract Dates
Contract dates represent commitments made to the customer:
| Date | Description |
|---|---|
| Contract Start Date | The promised date when production will begin |
| Contract Finish Date | The promised completion date for the project |
These dates are typically set when the contract is signed and are used to measure on-time delivery performance.
Updating Dates from Contracts
When a project proposal contract is fully signed, the system automatically calculates and sets production dates based on contract terms.
Contract Fields Used:
| Contract Field | Description |
|---|---|
| Starts Within | Number of days or weeks until production begins |
| Project Duration | Length of production in days or weeks |
Production Fields Updated:
| Production Field | Calculation |
|---|---|
| Contract Start Date | Today + Starts Within |
| Contract Finish Date | Start Date + Project Duration |
| Predicted Start Date | Same as Contract Start Date |
| Predicted Finish Date | Same as Contract Finish Date |
| Duration (weeks) | Calculated from Project Duration |
Example:
If a contract is signed today (January 15) with:
- Starts Within: 2 weeks
- Project Duration: 8 weeks
The system sets:
- Contract Start Date: January 29
- Contract Finish Date: March 26
Date calculations use business days - weekends (Saturday and Sunday) and company holidays are automatically excluded.
- 1 week = 5 business days
- If a holiday falls within the calculation period, the date extends accordingly
Example: If "Starts Within" is set to 2 weeks and there's a company holiday during that period, the start date will be pushed out by one additional day to maintain 10 business days.
Configure your company holidays in Settings → Company Holidays to ensure accurate date calculations.
Production dates are only calculated when the contract is fully signed by all parties. Draft or partially signed contracts do not affect production dates.
Predicted Dates and Duration
Predicted dates are internal planning estimates that help schedule resources and track progress:
| Field | Description |
|---|---|
| Predicted Start Date | When production is expected to start |
| Predicted Finish Date | When production is expected to finish (auto-calculated) |
| Duration | Length of production in weeks |
How Duration Calculation Works
The Predicted Start Date, Predicted Finish Date, and Duration fields work together with bidirectional synchronization. When you change one field, the others automatically update:
Calculation Rules:
- Set Duration → Predicted Finish Date auto-calculates from Predicted Start Date + Duration
- Set Predicted Finish Date → Duration auto-calculates based on business days between start and finish
- Change Predicted Start Date → Predicted Finish Date recalculates (Duration stays the same)
Business Days:
- Duration is measured in business days, not calendar days
- 1 week = 5 business days
- Weekends (Saturday and Sunday) are automatically skipped
- Company holidays are automatically excluded from the calculation
Example:
| Scenario | Predicted Start | Duration | Predicted Finish |
|---|---|---|---|
| Set duration to 2 weeks | Jan 6 (Mon) | 2 weeks | Jan 17 (Fri) |
| Change finish to Jan 24 | Jan 6 (Mon) | 3 weeks (auto) | Jan 24 (Fri) |
| Holiday on Jan 20 | Jan 6 (Mon) | 3 weeks | Jan 27 (Mon)* |
*When a holiday falls within the duration, the finish date extends to maintain the same number of business days.
Only set two of the three fields - the system calculates the third automatically. Most users set the Predicted Start Date and Duration, letting the system calculate the finish date.
Actual Dates
Actual dates record when work really happened:
| Date | Description |
|---|---|
| Actual Start Date | When production work actually began |
| Actual Finish Date | When all production work was completed |
| Substantial Completion Date | When the project became usable by the owner |
Substantial Completion
Substantial Completion marks when a construction project is deemed sufficiently completed to the point where the owner can use it for its intended purpose. This is a key milestone for tracking project performance and triggering contractual obligations.
What is Substantial Completion?
Substantial Completion is the point at which:
- The main construction work is finished
- The project is ready for final walkthrough
- Only minor punch list items may remain
- The project can be occupied or used for its intended purpose
The Substantial Completion Date and Actual Finish Date are separate fields. Substantial Completion tracks when the project became usable by the owner, while Actual Finish Date tracks when all production work was completed. In many cases these dates are the same, but they can differ when minor work continues after the owner takes occupancy.
How It's Set
The Substantial Completion Date is automatically set when you move a project to the Complete production stage (if not already set). You can also manually set or adjust this date in the project details.
On-Time Delivery
A project is considered on time if the Substantial Completion Date is on or before the Contract Finish Date:
- On Time: Substantial Completion ≤ Contract Finish Date
- Late: Substantial Completion > Contract Finish Date
This metric is tracked in production dashboard KPIs and on-time delivery reports.
Date Summary
| Date Type | Field | Purpose | How It's Set |
|---|---|---|---|
| Contract | Contract Start Date | Customer commitment | Manual entry |
| Contract | Contract Finish Date | Customer commitment | Manual entry |
| Predicted | Predicted Start Date | Planning estimate | Manual entry |
| Predicted | Predicted Finish Date | Planning estimate | Auto-calculated or manual |
| Predicted | Duration | Production length | Auto-calculated or manual |
| Actual | Actual Start Date | Real start | Manual or stage change |
| Actual | Actual Finish Date | All work completed | Auto on "Complete" stage |
| Actual | Substantial Completion Date | Owner can use project | Auto on "Complete" stage (if not set) |
Construction Schedule
View and manage the project schedule:
- Gantt Chart - Visual timeline of tasks
- Task List - All scheduled activities
- Milestones - Key project dates
Managing the Schedule
- Add tasks with start and end dates
- Assign to team members or subcontractors
- Set dependencies between tasks
- Track actual vs. planned progress
Daily Logs
Record daily construction activity:
- Weather conditions
- Crew members on site
- Work performed
- Photos and notes
See Daily Logs for detailed information.
Percent Complete
Track overall project progress:
- Update percent complete manually or
- Let the system calculate from completed tasks
- View progress in the production widget
Punch List
Manage pre-completion items:
- Add punch list items
- Assign responsibility
- Track completion
- Include photos
Production Metrics
Key metrics include:
- Days in production (Actual Start to Actual Finish)
- On-time delivery rate (Substantial Completion vs. Contract Finish)
- Predicted vs. actual timeline variance
- Percent complete
- Days to predicted completion
Production Team
Assign production team members:
- Project Manager - Overall production oversight
- Lead Remodeler - On-site supervision
- Subcontractors - Trade-specific work
Related Topics
- Daily Logs - Recording daily activity
- Schedule - Project scheduling
- Job Costing - Tracking project costs