Cost Detail Report

Required Permission
View Project Costs - You must have the View Project Costs permission to access this report.
Filtered Data

This report is filtered based on your division settings:

  • Function: Operational
  • Work Type: Full Project

The Cost Detail report compares what each completed project sold for with its estimated and actual cost, and sums the results for the date range: total costs, margins, losses, and how many jobs came in over or under estimate.

note

This report now requires View Project Costs, the same permission as the WIP Report. Before October 2026 it had no permission check. If someone who used it can no longer open it, an administrator can grant them that permission.

Accessing the Report​

Reports > Production > Cost Detail

The report reads actual cost imported from ComputerEase, so it appears in the menu only for companies that import it.

Which Projects Are Counted​

Won production projects (not change orders) whose Completion Date falls in the date range. Deleted projects, projects on deleted contacts and projects marked as non-sale are left out, as on the other production reports.

note

Before October 2026 this report also counted non-sale projects and projects on deleted contacts, so totals for earlier ranges can differ slightly from what it showed then.

Summary​

FigureHow it is worked out
Total ProjectsProjects in the range
Total Sold AmountSum of each project's total sold amount
Total Actual CostSum of actual cost
Total Estimated CostSum of estimated cost
Cost DifferenceTotal Estimated Cost − Total Actual Cost. Shown in red when negative
Cost Difference AverageCost Difference ÷ Total Projects
Cost Difference PercentCost Difference ÷ Total Sold Amount
Total LossesSum of (estimated − actual cost) over the projects that cost more than estimated
Total Losses Project PercentTotal Losses ÷ Total Sold Amount
Avg. Project SizeTotal Sold Amount ÷ Total Projects
Estimated Margin(Total Sold − Total Estimated Cost) ÷ Total Sold, across all projects together
Actual Margin(Total Sold − Total Actual Cost) ÷ Total Sold, across all projects together
Margin DifferenceActual Margin − Estimated Margin
Performance RatioProjects that came in at or under their estimated cost : projects that cost more. A range where every job came in on budget reads like 12:0
Performance RateThe share of projects that came in at or under their estimated cost. Higher is better

The margins are worked out across all projects together, so a large project counts for more than a small one, as it does in the cost totals.

note

Before October 2026, Performance Rate counted the projects that cost more than estimated, the opposite of its label. It now counts the ones that came in at or under, so the figure for the same range is 100% minus what it used to show.

Report Columns​

ColumnDescription
Project IDJob number. Click it to open the project
NameClient last name and project title
Total Sold AmountThe project's total sold amount
Total Actual CostActual cost
Total Estimated CostEstimated cost
Actual Margin(Sold − actual cost) ÷ sold
Estimated Margin(Sold − estimated cost) ÷ sold
Margin DifferenceActual Margin − Estimated Margin
Date StartedProduction start date
Date CompleteProduction completion date
Project ManagerThe project manager
Lead RemodelerThe project's lead carpenter
SalespersonThe salesperson
DivisionThe project's division
Cost DifferenceEstimated cost − actual cost

Project Manager, Lead Remodeler, Salesperson and Division use your company's names for those fields. A cost or sold amount with no value shows as $ — —, and a margin that cannot be worked out shows as 0.00%. The TOTAL row repeats the summary's totals and margins, with the Performance Ratio under Margin Difference.

The report opens in project-title order. Click any column heading to sort by it.

Available Filters​

FilterDescription
Completion Date From / ToThe completion-date range. Defaults to January 1 through today. Presets pick common ranges
UserProjects where this person is the salesperson, project manager, planning team leader, estimator, inside sales, lead carpenter or lead painter. Disabled users are listed after the others, marked (disabled)
DivisionOnly projects in this division. Shown when your company does not use the Division / Function / Work Type filters. Deleted divisions are marked (Disabled)
Division / Function / Work TypeShown instead of the single Division filter when your company uses them. See the data scope note at the top of this page

Filters are kept in the page address, so you can bookmark or share a filtered view.

Exporting​

Click Export CSV to download the table in the order shown, followed by its TOTAL row. Amounts and margins are plain numbers.